Written and maintained by the PhDino author · Last reviewed 21 September 2026 · A documented rule of thumb, pinned by automated tests · how PhDino checks its numbers
Related standards: ACI 211.1
Turning a volume of concrete into bags of cement, sand, gravel, and water using a simple proportion mix.
Concrete is really two things combined: cement paste (Portland cement plus water) and aggregate (sand plus gravel or crushed stone) that the paste binds together. The paste does the chemical work of hardening; the aggregate is there mostly to fill volume cheaply and add bulk strength, since aggregate is far less expensive than cement paste itself.
A common DIY approach specifies the mix as a simple volume ratio — for example 1:2:3 (cement:sand:gravel) for general-purpose concrete work — rather than a full lab-verified mix design. That ratio, plus a target water-cement ratio, is enough to estimate quantities for a small pour.
One detail trips people up the first time: the dry, loose ingredients occupy noticeably more volume than the wet concrete they produce. Loose sand and gravel have air gaps between the particles; once mixed with cement paste and placed, those gaps collapse as the paste fills them. A commonly used rule of thumb is that the dry loose volume runs about 1.54 times the finished wet concrete volume — which is why "1 cubic yard of concrete" needs noticeably more than 1 cubic yard of loose dry materials on hand.
Dry volume ≈ 1.54 × wet concrete volume Each component volume = dry volume × (its ratio ÷ sum of ratios) Mixing water = cement weight × water-cement ratio
PhDino earns a commission on qualifying purchases made through this link, at no extra cost to you.
Building Construction Illustrated by Francis D. K. Ching — A drawn, plain-language guide to how buildings and their materials go together. (Bookshop.org UK, UK delivery only)
→ The full PhDino bookshelf on Bookshop.org (UK delivery only)