Written and maintained by the PhDino author · Last reviewed 21 September 2026 · Checked against 2 independent reference calculations · how PhDino checks its numbers
Converting a slab or footing's dimensions into the cubic yards ready-mix concrete is actually sold in.
Ready-mix concrete in the US is ordered and delivered by the cubic yard, not the cubic foot — so the first real step in planning any pour is converting a slab or footing's length, width, and thickness into that unit. It sounds trivial, but it's the single most common source of an underestimated order.
A waste margin matters more than it looks like it should. Subgrade is rarely perfectly flat, formwork is never perfectly plumb, and some concrete is lost to spillage and to filling the low spots a laser level didn't catch. Coming up short mid-pour means a second truck, a cold joint where the two placements meet, and a rushed call to the batch plant — all avoidable with a modest margin built in up front.
Volume (ft³) = Length × Width × Thickness Volume (yd³) = Volume (ft³) ÷ 27
Use this to turn the dimensions of a slab, pad, footing or step into the amount of concrete to order, in cubic feet and in cubic yards, which is the unit ready-mix suppliers sell by. It also adds a margin for the concrete you will inevitably lose, so the number you get is the number to phone in.
Measure the length and width of the finished shape, enter the thickness in inches, and choose a waste margin. For a shape that is not a rectangle, split it into rectangles and add the results, or use π × radius² for a round pad.
A single-car-and-workshop garage slab measures 24 ft by 20 ft and is 5 in thick. The subgrade is graded but not perfectly flat, so a 7% allowance is used. How much ready-mix should be ordered?
| You enter | Value |
|---|---|
| Length | 24 ft |
| Width | 20 ft |
| Thickness | 5 in |
| Waste/Spill Margin | 7 % |
| The calculator returns | Value |
|---|---|
| Volume | 200.0 ft³ |
| Volume | 7.41 yd³ |
| Order This Much | 7.93 yd³ |
Worked by hand:
Order 8 cubic yards. Ready-mix is delivered in truckloads and priced by the yard, and that job would be hopeless to mix from bags. One more inch of thickness would add 1.48 yd³ of concrete, and making the whole slab 6 inches thick would raise the order to 9.5 yd³, which shows how sensitive the total is to the thickness on the plans.
Running out of concrete mid-pour is far more expensive than having a little left over, because a cold joint forms where the second load meets the first. That is why the waste allowance is included by default and why it is better to round the final figure up to the next quarter or half yard than down.
About 45 bags of 80 lb mix, since each yields roughly 0.6 ft³ and a yard is 27 ft³. It is much more practical to order ready-mix above a yard or so.
Four inches is common for patios and walks, and five to six for garage floors and driveways, but the right thickness depends on the load, the soil and local practice. Follow your plans or building department rather than a rule of thumb.
Five to ten percent is typical, with the higher end for uneven subgrade, complicated shapes or a pour that will be placed by hand. If you are unsure, round the total up to the next half yard.
For a circle use π × radius² × thickness, and for a round column π × radius² × height. This calculator handles rectangles, so calculate the round shape separately and add it in cubic feet.
PhDino earns a commission on qualifying purchases made through this link, at no extra cost to you.
Building Construction Illustrated by Francis D. K. Ching — A drawn, plain-language guide to how buildings and their materials go together. (Bookshop.org UK, UK delivery only)
→ The full PhDino bookshelf on Bookshop.org (UK delivery only)