Working out cut volume and how many truck loads it takes to haul the spoil off site.
Soil sitting undisturbed in the ground (bank volume) has been compacted by its own weight, and often by whatever was built on top of it, over a long time. The moment it's dug up, that structure is broken apart and the soil particles no longer pack as tightly — so the same mass of soil now occupies more volume. This is called swell, and it's why "I dug a 10 cubic yard hole" and "I have 10 cubic yards of dirt to haul away" are two different numbers.
Swell varies with soil type: loose sand swells relatively little, while a dense clay can swell substantially more, since clay's particle structure collapses more dramatically once disturbed. When in doubt, a conservative (higher) swell factor avoids showing up with too few trucks.
Bank volume (yd³) = Length × Width × Depth ÷ 27 Trucked volume = Bank volume × (1 + swell %) Truck loads = Trucked volume ÷ truck capacity, rounded up
PhDino earns a commission on qualifying purchases made through this link, at no extra cost to you.
Building Construction Illustrated by Francis D. K. Ching — A drawn, plain-language guide to how buildings and their materials go together. (Bookshop.org UK, UK delivery only)
→ The full PhDino bookshelf on Bookshop.org (UK delivery only)